Rivervale Water and Street Lighting Service Water System Intake Upgrades
Federal contribution
$42,126
Federal share50%
of $84.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Kootenay Boundary
- Construction start
- Jun 12, 2017(actual)
- Construction end
- Nov 30, 2017(actual)
Against the original forecast
- Construction start3 months earlyforecast Sep 11, 2017
- Construction end4 weeks lateforecast Oct 31, 2017
Also in Trail
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49833 in the federal list. How to read these figures.