Back to projects

Main Street to Victoria Drive Watermain Looping

Smithers, British Columbia

completeDrinking WaterCWWF
Federal contribution
$282,500
Federal share50%

of $565.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Smithers
Construction start
Oct 17, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 14, 2017
  • Construction end4 months lateforecast Aug 31, 2018

Also in Smithers

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49837 in the federal list. How to read these figures.