Thompson-Nicola Regional District (TNRD) Utility Systems Master Plan
Federal contribution
$75,736
Federal share50%
of $151.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Thompson-Nicola
- Construction start
- Nov 30, 2017(actual)
- Construction end
- Feb 28, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Apr 1, 2017
- Construction end4 weeks earlyforecast Mar 31, 2018
Also in Kamloops
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49849 in the federal list. How to read these figures.