Thompson-Nicola Regional District (TNRD) Utility Systems Master Plan

Kamloops, British Columbia

completeDrinking WaterCWWF
Federal contribution
$75,736
Federal share50%

of $151.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
Nov 30, 2017(actual)
Construction end
Feb 28, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 1, 2017
  • Construction end4 weeks earlyforecast Mar 31, 2018