Wastewater System Condition Assessment and Optimization

Tahsis, British Columbia

completeWastewaterCWWF
Federal contribution
$120,147
Federal share50%

of $240.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Tahsis
Construction start
Jun 1, 2017(actual)
Construction end
Mar 30, 2018(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Apr 3, 2017
  • Construction end4 weeks lateforecast Feb 28, 2018

Also in Tahsis

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49865 in the federal list. How to read these figures.