Back to projects

Water System Improvements

Squamish, British Columbia

completeDrinking WaterCWWF
Federal contribution
$644,361
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
Built
Program
Clean Water and Wastewater Fund
Construction start
Jul 31, 2017(actual)
Construction end
Dec 15, 2017(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Nov 30, 2017