Wastewater Treatment Plant N-VIRO Building Upgrades
Federal contribution
$521,702
Federal share46%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Banff
- Construction start
- Apr 30, 2018(actual)
- Construction end
- Mar 20, 2019(actual)
Against the original forecast
- Construction start12 months lateforecast Apr 30, 2017
Also in Banff
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49942 in the federal list. How to read these figures.