Replacement of Chlorination Pump at Alpine water treatment plant
Federal contribution
$1,250
Federal share50%
of $2.5K total eligible cost; the rest comes from other partners.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Trent Lakes
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Jul 31, 2017(actual)
Also in Trent Lakes
- Reconstruction of Beaver Lake Road$755.4K
- Replacement of the Existing Standby Generator at Buckhorn Lake Estates$20.6K
- Replacement of Existing Highlift Pumps (2) at Buckhorn Lake Estates$13.0K
- Addition of standby filter cartridge housing for Alpine Water treatment plant$3.8K
- Installation of Two (2) sample hydrants and One (1) Flushing hydrant at Buckhorn Lake Estates$2.6K