Water Distribution System Upgrade
Federal contribution
$51,992
Federal share50%
of $104.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
2017
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Gravelbourg
- Construction start
- Aug 30, 2016(actual)
- Construction end
- Aug 25, 2017(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Oct 1, 2016
- Construction end7 months earlyforecast Mar 31, 2018
Also in Gravelbourg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50023 in the federal list. How to read these figures.