Water Distribution System Upgrade

Gravelbourg, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$51,992
Federal share50%

of $104.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
2017
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Gravelbourg
Construction start
Aug 30, 2016(actual)
Construction end
Aug 25, 2017(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Oct 1, 2016
  • Construction end7 months earlyforecast Mar 31, 2018