Watermain rehabilitation and water and wastewater servicing: Snyder Avenue North and William Street in Elmira.
Federal contribution
$456,901
Federal share22%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Woolwich
- Construction start
- Apr 12, 2017(actual)
- Construction end
- Sep 15, 2017(actual)
Against the original forecast
- Construction end2 weeks lateforecast Sep 1, 2017
Also in Woolwich
- West Montrose Covered Bridge Rehabilitation$2.5M
- Rehabilitation of the Weigel Stormwater Management Drain$899.9K
- Woolwich Memorial Centre - Refrigeration Plant and Dehumidifier Replacement$792.0K
- Regional Road 22 (Northfield Drive) from Line 86 to Waterloo/Wellington Boundary$723.0K
- Rehabilitation of the Glasgow Street South Bridge in Conestogo$704.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50077 in the federal list. How to read these figures.