Wharf Restoration
Federal contribution
$378,521
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2017
201820192020202120222023
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of St. Stephen
- Construction start
- Jul 3, 2019(actual)
- Construction end
- Mar 13, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2019
- Construction end5 months lateforecast Oct 1, 2022
Also in St. Stephen
- Garcelon Civic Centre$6.2M
- Milltown Boulevard (King Street to Hawthorne Street) - Watermain and Sanitary Sewer Renewal$1.3M
- Elm Park, Pinewood, and Maple - Sewer Separation and Infrastructure Renewal$1.3M
- Combined Sewer Elimination & Water Main Renewal$1.2M
- Combined Sewer Separation and Utility Renewal - Union Street$1.1M