Water Pollution Control Plant- Disinfection (E. Coli) and Preliminary Treatment (Headworks) Upgrades

Cochrane, Ontario

completeWastewaterCWWF
Federal contribution
$346,907
Federal share32%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Cochrane
Construction start
Oct 10, 2017(actual)
Construction end
Mar 27, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2017