Waterproof existing valve chamber on raw water main

Georgian Bluffs, Ontario

completeDrinking WaterCWWF
Federal contribution
$5,777
Federal share29%

of $20.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2017
2018
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Georgian Bluffs
Construction start
Jul 1, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 20, 2017
  • Construction end2 months lateforecast Oct 31, 2017