Waterproof existing valve chamber on raw water main
Federal contribution
$5,777
Federal share29%
of $20.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2017
2018
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Georgian Bluffs
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Dec 31, 2017(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 20, 2017
- Construction end2 months lateforecast Oct 31, 2017
Also in Georgian Bluffs
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50117 in the federal list. How to read these figures.