Rehabilitation of Greavette Storm Sewer/Drainage System at 325 Greavette Street that serves 11 hectares of the urban core

Gravenhurst, Ontario

completeWastewaterCWWF
Federal contribution
$14,400
Federal share2%

of $800.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2017
201820192020
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 9, 2018(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start15 months lateforecast Apr 1, 2017