Construction of a community center
Federal contribution
$241,215
Federal share33%
of $723.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2017
20182019202020212022
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Donnacona
- Construction start
- Apr 20, 2020(actual)
- Construction end
- May 30, 2022(actual)
Against the original forecast
- Construction start2.9 years lateforecast Jun 1, 2017
- Construction end4.5 years lateforecast Nov 29, 2017
Also in Donnacona