Construction of a New Konkle Creek Stormwater Naturalization Corridor

Lincoln, Ontario

completeWastewaterCWWF
Federal contribution
$397,306
Federal share23%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Lincoln
Construction start
Aug 18, 2017(actual)
Construction end
Nov 23, 2018(actual)

Against the original forecast

  • Construction start7 months lateforecast Jan 9, 2017