Back to projects

Wastewater pipe rehabilitation at 327 Edward Street

Powassan, Ontario

completeWastewaterCWWF
Federal contribution
$2,500
Federal share50%

of $5.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Powassan
Construction start
Mar 1, 2018(actual)
Construction end
Apr 5, 2018(actual)

Against the original forecast

  • Construction start7 months lateforecast Aug 1, 2017

Also in Powassan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50200 in the federal list. How to read these figures.