Flow Meter Replacement for Sewage Lift Station #2

Powassan, Ontario

completeWastewaterCWWF
Federal contribution
$3,194
Federal share32%

of $10.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Powassan
Construction start
Jun 12, 2017(actual)
Construction end
Apr 30, 2018(actual)