Upgrade Pump at Sewage Lift Station #2
Federal contribution
$4,000
Federal share50%
of $8.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Powassan
- Construction start
- Oct 15, 2017(actual)
- Construction end
- Oct 30, 2017(actual)
Against the original forecast
- Construction start5 months lateforecast May 15, 2017
- Construction end5 months lateforecast May 16, 2017
Also in Powassan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50203 in the federal list. How to read these figures.