Rehabilitate Stormwater Management Facility 19-1 Bayview Avenue and Major Mackenzie Avenue

Richmond Hill, Ontario

completeWastewaterCWWF
Federal contribution
$417,500
Federal share50%

of $835.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
2017201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Richmond Hill
Construction start
Jan 15, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast Oct 31, 2016
  • Construction end5 months lateforecast Oct 31, 2019