Back to projects

Rehabilitate Stormwater Management Facility 19-5 Leslie Avenue and Elgin Mills Road

Richmond Hill, Ontario

completeWastewaterCWWF
Federal contribution
$202,500
Federal share50%

of $405.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
20172018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Richmond Hill
Construction start
Jan 15, 2017(actual)
Construction end
Jul 3, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Oct 31, 2016
  • Construction end4 months earlyforecast Oct 31, 2018

Also in Richmond Hill

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50211 in the federal list. How to read these figures.