Replacement of 700m of watermain on Trench Street (From Major Mackenzie Drive to Mill Street)
Federal contribution
$410,300
Federal share50%
of $820.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Richmond Hill
- Construction start
- Sep 18, 2017(actual)
- Construction end
- May 4, 2018(actual)
Against the original forecast
- Construction start11 months lateforecast Oct 31, 2016
- Construction end4 weeks earlyforecast May 31, 2018
Also in Richmond Hill
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50212 in the federal list. How to read these figures.