Replacement of 310m of watermain on Laverock Avenue (From Lucas Street to west limit)
Federal contribution
$210,250
Federal share50%
of $420.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Richmond Hill
- Construction start
- Oct 18, 2017(actual)
- Construction end
- Dec 15, 2017(actual)
Against the original forecast
- Construction start12 months lateforecast Oct 31, 2016
- Construction end3 months earlyforecast Mar 31, 2018