Replacement of 525m of watermain on Kersey Crescent (From Weldrick Road West to May Avenue)

Richmond Hill, Ontario

completeDrinking WaterCWWF
Federal contribution
$350,550
Federal share50%

of $701.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Richmond Hill
Construction start
Nov 20, 2017(actual)
Construction end
May 4, 2018(actual)

Against the original forecast

  • Construction start13 months lateforecast Oct 31, 2016
  • Construction end4 weeks earlyforecast May 31, 2018