Hydraulic Flow Assessment for the entire villages of Morrisburg and Iroquois serving approximately 2,200 households

South Dundas, Ontario

completeDrinking WaterCWWF
Federal contribution
$15,372
Federal share31%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Mar 2, 2017(actual)
Construction end
Jun 30, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast Jan 1, 2017
  • Construction end11 months lateforecast Aug 1, 2018