Rehabilitation and Realignment of Stormwater Drains for Paget and Rolling Meadows

Tillsonburg, Ontario

completeWastewaterCWWF
Federal contribution
$50,000
Federal share29%

of $175.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Tillsonburg
Construction start
Jun 22, 2017(actual)
Construction end
May 31, 2018(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2017
  • Construction end6 months lateforecast Nov 30, 2017

Also in Tillsonburg