Back to projects

Relining of Sanitary Sewer Lines along Town Creek

Timmins, Ontario

completeWastewaterCWWF
Federal contribution
$925,000
Federal share50%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Timmins
Construction start
Dec 5, 2017(actual)
Construction end
Dec 2, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast Jun 1, 2017
  • Construction end3 months lateforecast Sep 6, 2019

Also in Timmins

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50279 in the federal list. How to read these figures.