Back to projects

Murray Street Water - Replacement of cast-iron watermain

Fort Erie, Ontario

completeWastewaterCWWF
Federal contribution
$163,600
Federal share50%

of $327.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 27, 2017
201820192020
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Fort Erie
Construction start
Apr 23, 2018(actual)
Construction end
Oct 30, 2020(actual)

Against the original forecast

  • Construction start12 months lateforecast Apr 30, 2017
  • Construction end12 months lateforecast Oct 31, 2019

Also in Fort Erie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50369 in the federal list. How to read these figures.