Murray Street Water - Replacement of cast-iron watermain
Federal contribution
$163,600
Federal share50%
of $327.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 27, 2017
201820192020
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Fort Erie
- Construction start
- Apr 23, 2018(actual)
- Construction end
- Oct 30, 2020(actual)
Against the original forecast
- Construction start12 months lateforecast Apr 30, 2017
- Construction end12 months lateforecast Oct 31, 2019
Also in Fort Erie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50369 in the federal list. How to read these figures.