Signs for Safety - Project 1
North Battleford, Saskatchewan
Federal contribution
$500
Federal share50%
of $1.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Battlefords Trail Breakers
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in North Battleford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50432 in the federal list. How to read these figures.