West Harrison Trail Network Upgrading and Maintenance
Federal contribution
$19,880
Federal share50%
of $40.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 14 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Lower Mainland ATV Club: LMATV
- Construction start
- Feb 14, 2015(actual)
- Construction end
- Dec 30, 2015(actual)
Also in Coquitlam