Snowmobile Barrier Installation
Federal contribution
$27,909
Federal share22%
of $128.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Club de Motoneige les Fusées Blanches
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)