Back to projects

French River Multi-Use Trail Expansion

French River, Ontario

completeRecreationNRT
Federal contribution
$13,016
Federal share43%

of $30.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 13 months before the announcement.

Program
National Recreational Trails Program
Construction start
May 1, 2015(actual)
Construction end
Nov 25, 2015(actual)

Also in French River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50841 in the federal list. How to read these figures.