Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 13 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
City of London
Construction start
Jul 6, 2015(actual)
Construction end
Nov 20, 2015(actual)