The Coves ESA East Pond Connections
Federal contribution
$45,000
Federal share15%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- City of London
- Construction start
- Jul 6, 2015(actual)
- Construction end
- Nov 20, 2015(actual)
Also in London