SIA-IAT Québec Upgrade and Improvement

Matane, Quebec

completeActive TransportationNRT
Federal contribution
$71,875
Federal share43%

of $166.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2009
2010
Built

Approved 2 months before the announcement.

Program
National Recreational Trails Program
Construction start
May 26, 2009(actual)
Construction end
Mar 31, 2010(actual)

Also in Matane