Snowmobile Trail Warm Up Shelter

North Battleford, Saskatchewan

completeRecreationNRT
Federal contribution
$4,350
Federal share36%

of $12.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
20152016
Built

Approved 16 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
Battlefords Trail Breakers
Construction start
Nov 24, 2014(actual)
Construction end
Jan 21, 2015(actual)

Also in North Battleford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51113 in the federal list. How to read these figures.