Huron Street sanitary sewer main relining

Deep River, Ontario

completeWastewaterCWWF
Federal contribution
$12,200
Federal share50%

of $24.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
2018202020222024
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Deep River
Construction start
Feb 8, 2018(actual)
Construction end
May 1, 2025(actual)

Against the original forecast

  • Construction start8 months lateforecast Jun 1, 2017
  • Construction end19 months lateforecast Sep 30, 2023