Huron Street sanitary sewer main relining
Federal contribution
$12,200
Federal share50%
of $24.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2017
2018202020222024
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Deep River
- Construction start
- Feb 8, 2018(actual)
- Construction end
- May 1, 2025(actual)
Against the original forecast
- Construction start8 months lateforecast Jun 1, 2017
- Construction end19 months lateforecast Sep 30, 2023
Also in Deep River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51134 in the federal list. How to read these figures.