Restoration of storm drain outfall
Chippewas of Rama First Nation, Ontario
Federal contribution
$67,500
Federal share50%
of $135.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
20182019
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Chippewas of Rama First Nation
- Construction start
- Nov 5, 2017(actual)
- Construction end
- Jun 4, 2019(actual)
Against the original forecast
- Construction end2 months lateforecast Mar 31, 2019
Also in Chippewas of Rama First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51148 in the federal list. How to read these figures.