Back to projects

Restoration of stormdrain outfall

Chippewas of Rama First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$1,853
Federal share23%

of $8.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 1, 2018(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 20, 2017
  • Construction end9 months lateforecast Dec 15, 2017

Also in Chippewas of Rama First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51159 in the federal list. How to read these figures.