Back to projects

Restoration of stormdrain outfall

Chippewas of Rama First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$4,009
Federal share33%

of $12.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Mar 26, 2018(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast Jul 15, 2017
  • Construction end3 months lateforecast Jun 30, 2018

Also in Chippewas of Rama First Nation