Upgrading of no. 2 highlight pumps at the water treatment plant
Federal contribution
$93,446
Federal share44%
of $210.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2017
20172018
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the Town of Kirkland Lake
- Construction start
- Jan 4, 2017(actual)
- Construction end
- Apr 25, 2018(actual)
Against the original forecast
- Construction start2 months earlyforecast Mar 6, 2017
- Construction end4 weeks lateforecast Mar 31, 2018
Also in Kirkland Lake
- Kirkland Lake Wastewater Improvement$16.0M
- Creating a Net Zero Indigenous Community Hub in Northern Ontario$3.0M
- Swastika Sewer System Upgrade / Swastika Water Pollution Control Plant Decommissioning$2.7M
- Equipment Upgrades to Joe Mavrinac Community Complex$2.4M
- Reconstruction of Taylor Avenue and Prospect Avenue$659.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51195 in the federal list. How to read these figures.