Upgrading of no. 2 highlight pumps at the water treatment plant

Kirkland Lake, Ontario

completeDrinking WaterCWWF
Federal contribution
$93,446
Federal share44%

of $210.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
20172018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jan 4, 2017(actual)
Construction end
Apr 25, 2018(actual)

Against the original forecast

  • Construction start2 months earlyforecast Mar 6, 2017
  • Construction end4 weeks lateforecast Mar 31, 2018