Clear Creek Bridge Rehabilitation
Federal contribution
$1.2M
$1,236,314
Federal share75%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2017
2018
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Government of Yukon
- Construction start
- Jun 13, 2017(actual)
- Construction end
- Aug 1, 2018(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Sep 1, 2018
Also in Dawson City
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51311 in the federal list. How to read these figures.