Dempster Highway Culvert Replacements

Dawson City, Yukon

completeHighways and RoadsSCF
Federal contribution
$1.1M
$1,148,327
Federal share75%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2017
2018
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Government of Yukon
Construction start
Jul 26, 2017(actual)
Construction end
Nov 1, 2018(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 1, 2017
  • Construction end9 months earlyforecast Jul 30, 2019

Also in Dawson City

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51317 in the federal list. How to read these figures.