Mapping of Distribution System and Improvements to Water Distribution System

Mattagami First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$2,203
Federal share22%

of $10.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Mattagami First Nation
Construction start
Apr 1, 2018(actual)
Construction end
Feb 28, 2020(actual)

Against the original forecast

  • Construction start13 months lateforecast Mar 1, 2017
  • Construction end5 weeks earlyforecast Mar 31, 2020

Also in Mattagami First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51523 in the federal list. How to read these figures.