Improvements to the stormwater system
Mattagami First Nation, Ontario
Federal contribution
$12,500
Federal share50%
of $25.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Mattagami First Nation
- Construction start
- Jul 1, 2019(actual)
- Construction end
- Feb 28, 2020(actual)
Against the original forecast
- Construction start2.3 years lateforecast Mar 1, 2017
- Construction end5 weeks earlyforecast Mar 31, 2020
Also in Mattagami First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51557 in the federal list. How to read these figures.