Expansion of Storage Capacity at the Water Treatment Plant
Mattagami First Nation, Ontario
Federal contribution
$15,000
Federal share50%
of $30.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Mattagami First Nation
- Construction start
- Mar 1, 2018(actual)
- Construction end
- Feb 28, 2020(actual)
Against the original forecast
- Construction start14 months lateforecast Jan 1, 2017
- Construction end5 weeks earlyforecast Mar 31, 2020