Haines Junction Water and Wastewater Upgrades

Haines Junction, Yukon

completeWastewaterCWWF
Federal contribution
$3.0M
$3,039,207
Federal share71%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2017
201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Haines Junction
Construction start
Aug 11, 2017(actual)
Construction end
Jul 24, 2020(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Aug 31, 2017
  • Construction end7 months lateforecast Dec 31, 2019

Also in Haines Junction

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51541 in the federal list. How to read these figures.