completeDrinking WaterSCF
Federal contribution
$120,679
Federal share30%

of $395.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Springdale
Construction start
Aug 1, 2018(actual)
Construction end
Nov 18, 2018(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Sep 1, 2018
  • Construction end23 months earlyforecast Oct 31, 2020