Back to projects

New Pumphouse and Associated Work for St. Fintan's Area

St. George's, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$45,798
Federal share32%

of $144.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
2018201920202021
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Sep 9, 2020(actual)
Construction end
Aug 10, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast May 15, 2020
  • Construction end4 months earlyforecast Dec 17, 2021

Also in St. George's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51645 in the federal list. How to read these figures.