Lift Station Controls and SCADA upgrades

Stephenville Crossing, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$112,122
Federal share33%

of $336.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
2018201920202021
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jul 6, 2020(actual)
Construction end
Oct 18, 2021(actual)

Against the original forecast

  • Construction start7 months lateforecast Dec 1, 2019
  • Construction end3 weeks lateforecast Sep 30, 2021