Back to projects

WC O'Neill Arena Roof Refurbishment

Saint Andrews, New Brunswick

completeRecreationSCF
Federal contribution
$295,128
Federal share33%

of $885.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 2, 2017
2018
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Saint Andrews
Construction start
Nov 20, 2017(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Jul 4, 2017
  • Construction end4 weeks earlyforecast Sep 30, 2018

Also in Saint Andrews