WC O'Neill Arena Roof Refurbishment
Federal contribution
$295,128
Federal share33%
of $885.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 2, 2017
2018
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Saint Andrews
- Construction start
- Nov 20, 2017(actual)
- Construction end
- Aug 31, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Jul 4, 2017
- Construction end4 weeks earlyforecast Sep 30, 2018
Also in Saint Andrews
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51688 in the federal list. How to read these figures.