Chemical Building
Federal contribution
$2.2M
$2,230,870
Federal share50%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020202120222023
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Brandon
- Construction start
- Oct 7, 2019(actual)
- Construction end
- Oct 19, 2022(actual)
Against the original forecast
- Construction start8 weeks lateforecast Aug 12, 2019
- Construction end10 months lateforecast Dec 31, 2021