Back to projects

Chemical Building

Brandon, Manitoba

completeDrinking WaterCWWF
Federal contribution
$2.2M
$2,230,870
Federal share50%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020202120222023
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Brandon
Construction start
Oct 7, 2019(actual)
Construction end
Oct 19, 2022(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 12, 2019
  • Construction end10 months lateforecast Dec 31, 2021

Also in Brandon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51747 in the federal list. How to read these figures.